Do I need approvals to renovate my home in Dubai?
Yes — most communities require a NOC from the master developer or community management, and works touching structure, façades or drainage also need Dubai Municipality permits. We prepare and submit the entire approval package on your behalf, so you never have to queue at a service centre.
Can we stay living in the house during the renovation?
For kitchens, bathrooms or single rooms, usually yes — we isolate the work zones, control dust and keep water and power on elsewhere. For full villa renovations we recommend moving out for the heavy civil and MEP phase; we will tell you honestly which weeks matter most.
What is a turnkey renovation, and why does it matter?
Turnkey means one contract, one team and one point of contact covering design, approvals, construction, joinery, HVAC, landscaping, pools and handover. ACD Group maintains this complete capability in-house. Fewer handovers between unrelated suppliers mean stronger control of quality, communication, cost and programme.
What order do the works happen in?
Design and approvals first, then structural and civil works, then MEP (electrical, plumbing, AC), then plastering and waterproofing, then finishes and joinery, and finally deep clean, snagging and handover. Respecting that sequence is what protects your finishes — painting before AC commissioning, for example, ruins both.
Which materials last best in Dubai's climate?
High humidity, year-round AC and intense UV punish cheap materials fast. We specify marine-grade or well-sealed joinery near coastlines, UV-stable outdoor fabrics and paints, porcelain and natural stone where footfall is heavy, and ventilation details that stop condensation behind wardrobes and TV walls.
Can I renovate in phases instead of all at once?
Absolutely — many families renovate the kitchen and living areas first and bedrooms or landscaping later. We plan the services (electrical, plumbing, AC) with the whole house in mind even in phase one, so nothing built today has to be torn out tomorrow.
What aftercare and support do you provide?
Every project ends with a documented snag list, and our support continues well beyond handover — like the families in The Meadows and The Springs can tell you, we are still there long after the work is done.